Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
- A . Assess and prioritize the impact of the new law on the project plan.
- B . Update the project plan because the law is an obligation for the project.
- C . Minimize the scope to catch the cost and schedule baseline.
- D . Meet the sponsor to ask for additional time and budget increase.
Suggested Answer: A