During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
- A . Allow the agile team to decide what they are able to deliver in each iteration
- B . Ask the team for additional feedback and add tasks to the task board,
- C . Hold a brainstorming session to identify the root cause of the complaints.
- D . Document the customer's complaints and critical issues in the issue log.
Suggested Answer: C