A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

  • A . Meet with the project sponsor to explain that the project cannot be completed as planned
  • B . Meet with the technical lead to review the sprint plan
  • C . Meet with the product owner to confirm the minimum viable product (MVP) option
  • D . Meet with the project team and reprioritize the backlog

Show Answer Hide Answer

Suggested Answer: B

   