A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.
What should the project manager do?
- A . Meet with the project sponsor to explain that the project cannot be completed as planned
- B . Meet with the technical lead to review the sprint plan
- C . Meet with the product owner to confirm the minimum viable product (MVP) option
- D . Meet with the project team and reprioritize the backlog
Suggested Answer: B