Which two actions should the project manager take with regard to schedule analysis?

1 Posts
1 Users
0 Likes
184 Views
(@colmenerocarmelo)
Noble Member
Joined: 2 years ago
Posts: 746
Topic starter  

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

  • A . Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development
  • B . Evaluate the master schedule and perform fast tracking and task crashing
  • C . Look (or gaps in the different schedules to determine which major risks might evolve over time
  • D . Review the project schedules to ensure that all tasks end with milestones
  • E . Evaluate the schedules for interdependencies to establish the critical path

Show Answer Hide Answer

Suggested Answer: C,D

   