What should the project manager do?

1 Posts
1 Users
0 Likes
151 Views
(@hepnerjacques)
Noble Member
Joined: 2 years ago
Posts: 705
Topic starter  

A key project team member has exhibited high interest in a project. The input from this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

  • A . Reallocate tasks for the team member of concern so that work is handled by another team member.
  • B . Schedule a meeting to discuss recent observations with the team member.
  • C . Organize a team-building session with all of the team members.
  • D . Consult the resource allocation matrix to see if the team member is still required for the project.

Show Answer Hide Answer

Suggested Answer: B

   