A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.

What should the project manager do next?

  • A . Submit a change request to include the manual.
  • B . Add the needed manual and update the risk log.
  • C . Review the stakeholder engagement plan.
  • D . Review the terms and conditions of the contract.

Show Answer Hide Answer

Suggested Answer: D

   