An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
A. Prioritize project A over project B since A is an external project and B is an internal project.
B. Plan projectA in sprints, starting with the module that does not require machine learning skills.
C. Engage the human resource manager to employ a machine learning expert for project A.
D. Plan project A to start at the end of project B when the machine learning expert is available.
Notifications
Clear all
Topic starter
22/09/2022 11:46 pm
Suggested Answer: B