An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.
What should the project manager do?
- A . Ask the sponsor to approve inclusion of an additional iteration to the project
- B . Ask the team to include the contingency plan in the iteration backlog
- C . Help the team review the project approach to initiate the corrective actions
- D . Ask the sponsor for money to implement the contingency plan.
Suggested Answer: C