A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

  • A . Apply fast-tracking techniques to compress the schedule of the critical project
  • B . Analyze both projects to determine the most effective use of common resources
  • C . Use resource optimization to justify requesting more resources for the critical project.
  • D . Provide schedule optimization training to the project teams to improve their skills.

Show Answer Hide Answer

Suggested Answer: B

   