A company is conducting a digital transformation project that has a hard deadline.
The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?
- A . Implement a project newsletter so the different team members can be informed about the progress of each project.
- B . Combine all of the small projects into one big project so the team can collaborate better as one big team.
- C . Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.
- D . Make sure that each individual project schedule is aligned with the common deadlines.
Suggested Answer: C