Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

1 Posts
1 Users
0 Likes
137 Views
(@ripaharris)
Noble Member
Joined: 2 years ago
Posts: 737
Topic starter  

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

  • A . Implement a project newsletter so the different team members can be informed about the progress of each project.
  • B . Combine all of the small projects into one big project so the team can collaborate better as one big team.
  • C . Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.
  • D . Make sure that each individual project schedule is aligned with the common deadlines.

Show Answer Hide Answer

Suggested Answer: C

   