How should the project manager support their claim to the vendor?

1 Posts
1 Users
0 Likes
268 Views
(@benninkcarrol)
Noble Member
Joined: 2 years ago
Posts: 687
Topic starter  

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.

How should the project manager support their claim to the vendor?

  • A . Share unsuccessful results from previous projects with a similar scope
  • B . Provide the failed test results along with the agreed-upon acceptance criteria
  • C . Show that the acceptance criteria were changed by the vendor without approval.
  • D . Document in the risk log that the issues in the system were already identified

Show Answer Hide Answer

Suggested Answer: B

   