A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.
How should the project manager support their claim to the vendor?
- A . Share unsuccessful results from previous projects with a similar scope
- B . Provide the failed test results along with the agreed-upon acceptance criteria
- C . Show that the acceptance criteria were changed by the vendor without approval.
- D . Document in the risk log that the issues in the system were already identified
Suggested Answer: B