A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.
How should the project manager adjust their responsibilities accordingly?
- A . Become a servant leader by supporting team collaboration and removing impediments
- B . Delegate coordination activities to the product owner so the project manager can locus on managing collaboration
- C . Request a scrum master to focus on the collaboration while the project manager focuses on the coordination
- D . introduce new communication tools to the project team members
Suggested Answer: A