A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project.

How should the project manager adjust their responsibilities accordingly?

  • A . Become a servant leader by supporting team collaboration and removing impediments
  • B . Delegate coordination activities to the product owner so the project manager can locus on managing collaboration
  • C . Request a scrum master to focus on the collaboration while the project manager focuses on the coordination
  • D . introduce new communication tools to the project team members

Show Answer Hide Answer

Suggested Answer: A

   