The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project.
How should the project manager handle this request?
- A . Send this change request to the change control board (CCB) for approval.
- B . Approve the request for the specialized training.
- C . Reject the request as it does not impact the project deliverables.
- D . Validate if the training is within scope and budget.
Suggested Answer: D