How should the project manager handle this request?

1 Posts
1 Users
0 Likes
88 Views
 Man
(@shortinoman)
Noble Member
Joined: 2 years ago
Posts: 733
Topic starter  

The project manager has recently received funding approval for a training program for the entire project team but has not yet defined the most effective training course. One team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

  • A . Send this change request to the change control board (CCB) for approval.
  • B . Approve the request for the specialized training.
  • C . Reject the request as it does not impact the project deliverables.
  • D . Validate if the training is within scope and budget.

Show Answer Hide Answer

Suggested Answer: D

   