A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
- A . Service level agreement (SLA)
- B . Statement of work (SOW)
- C . Scope management plan
- D . Memorandum of understanding (MOU)
Suggested Answer: B