A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
- A . Postpone the required work on the project until school holidays begin
- B . Advise the school to close (or the duration of the project work
- C . Continue the work as planned and inform the school when the project team arrives on-site
- D . Liaise with the school to include nonworking project hours during school start and finish times
Suggested Answer: D