The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
- A . Estimate to complete
B. Estimate at completion
C. Original cost baseline
D. Cost performance index
Suggested Answer: B