A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations
What should the program manager do next?
- A . Reassign the component project manager to another component project or activity
B. Verify that the benefits were delivered and authorize component project closure
C. Conduct a program audit to confirm that the component protect is complete
D. Keep the component project open until the program benefits are realized
Suggested Answer: A