Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance

To resolve this situation, which of the following must go through critical review and change"?

  • A . Program Benefits Management domain
    B. Stakeholder communications requirements
    C. Program communications report
    D. Program communications management plan

Show Answer Hide Answer

Suggested Answer: B
 