i program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced
he program manager will use the qualified seller list to do which of the following?
- A . Plan a proposal evaluation system
B. Prepare the program procurement management plan
C. Perform the required program budget updates
D. Issue requests for proposals
Suggested Answer: D