A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

1 Posts
1 Users
0 Likes
167 Views
(@burlandeldridge)
Posts: 713
Noble Member
Topic starter
 

A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

  • A . Project submittal approval process
    B. RFI process
    C. Payment procedures
    D. Punch List process
    E. Project start and completion dates

Show Answer Hide Answer

Suggested Answer: B, E
 