When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)
- A . Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.
- B . It depends.
- C . Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.
- D . All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.
Suggested Answer: D