When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
- A . Yes, but only for Scrum Teams whose work has dependencies.
- B . Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.
- C . No, each Scrum Team stands alone.
- D . No, that is far too hard and must be done in a hardening Sprint.
Suggested Answer: B