When is implementation of a Product Backlog item considered complete?
- A . At the end of the Sprint.
- B . When the item has no work remaining in order to be potentially released.
- C . When QA reports that the item passes all acceptance criteria.
- D . When all work in the Sprint Backlog related to the item is finished.
Suggested Answer: B