When is the Sprint Backlog created?

  • A . At the beginning of the project.
  • B . During the Sprint Planning meeting.
  • C . Prior to the Sprint Planning meeting.
  • D . During the Sprint.

Show Answer Hide Answer

Suggested Answer: B

   