When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
- A . The Development Team.
- B . The Product Owner and all stakeholders.
- C . The Product Owner and the Development Team.
- D . The Scrum Master, project manager and Development Team.
Suggested Answer: C