As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint.

What should it do?

  • A . Inform the Product Owner at the Sprint Review, but prior to the demonstration.
  • B . Find another Scrum Team to give the excess work to.
  • C . As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
  • D . Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Show Answer Hide Answer

Suggested Answer: C

   