What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
- A . Put them on a separate list on the Scrum board, available for all to see.
- B . Add them to the Product Backlog and keep the Product Owner posted on the expected effort.
- C . Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.
- D . Add them to the definition of “Done” so the work is taken care of every Sprint.
Suggested Answer: B,D