A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary.
What action should the Scrum Master take?
- A . Call a meeting between the Development Team and senior management.
- B . Comply with the decision of the self-organizing team.
- C . Consult with the Product Owner to see how he/she feels about the situation.
- D . Begin facilitating productive and useful Sprint Retrospectives.
Suggested Answer: D