Notifications
Clear all
Topic starter
18/06/2022 4:51 am
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum.
What action should the Scrum Master take?
- A . Allow the Development Team to self-manage and determine for itself what to do.
- B . Set up the meeting and tell the Development Team that is how it will be done.
- C . Ask the Development Team members to alternate who is responsible for meeting setup.
- D . Inform management and ask them to solve it.
Suggested Answer: A