During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
- A . When the Product Owner identifies new work.
- B . As soon as possible after they are identified.
- C . When the Scrum Master has time to enter them.
- D . During the Daily Scrum after the Development Team approves them.
Suggested Answer: B