Topic starter
14/07/2022 7:13 pm
A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.
Which risk management strategy has been adopted in this scenario?
- A . Shared
- B . Accepted
- C . Enhanced
- D . Exploited
Suggested Answer: D