A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?
- A . Offer a new contract to the resource who is leaving.
- B . Establish a proactive knowledge-sharing plan.
- C . Update the risk register and inform the customer.
- D . Develop a contingency budget to replace the key resource.
Suggested Answer: C