What should the tea...
 
Notifications
Clear all

What should the team member do?

1 Posts
1 Users
0 Likes
163 Views
(@rippesteban)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

  • A . Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.
  • B . Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.
  • C . Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).
  • D . Inform the scrum master so that the change can be discussed directly with the stakeholder.

Show Answer Hide Answer

Suggested Answer: C

   
Quote

Latest PMI PMP Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: