A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.
What should the team member do?
- A . Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.
- B . Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.
- C . Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).
- D . Inform the scrum master so that the change can be discussed directly with the stakeholder.
Suggested Answer: C