What should the team do differently during planning for the next iteration"?

1 Posts
1 Users
0 Likes
148 Views
(@kossmangonzalo)
Noble Member
Joined: 2 years ago
Posts: 715
Topic starter  

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

  • A . Request the product owner and team facilitator to provide the size of the story
  • B . Average the story points provided by each team member for a story
  • C . Continue multiple rounds of planning poker and arrive at the size of the story
  • D . Collaborate with different teams and arrive at the size of the story

Show Answer Hide Answer

Suggested Answer: C

   