A complex project is m its execution phase. The project is set up to produce both predictive and incremental deliverables. The agile team is running late on their tasks There is a resource on the agile team who is responsible for producing progress reports for the project manager This resource has the required skills to help other team members with their workload
What should the project manager do to optimize the time of the resource who produces the progress reports?
- A . Work more closely with the agile team to eliminate the need for progress reports
- B . Record this in the issue log and find a resource to produce the reports
- C . Produce the progress reports on their own
- D . Engage a new resource to produce the progress reports
Suggested Answer: A