A project manager is leading a project that is on time and under budget. In the weekly meeting with the team, the project manager finds out that one of the tasks due next week does not have an assigned resource available for it. The resource is currently assigned to another project.
What should the project manager do to manage the situation?
- A . Ask the procurement department to supply a different resource.
- B . Change the schedule according to the availability of the resource.
- C . Ask the sponsor to obtain the resource as originally planned.
- D . Contact the other project manager to request the resource.
Suggested Answer: D