Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
- A . Schedule a dedicated session to review the team charter.
- B . Set up a meeting with the team member to review the team charter.
- C . Ask another team member to meet with this team member for a discussion.
- D . Send a reminder to the team member about the rule being violated.
Suggested Answer: B