The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date .
What should the project manager do next?
- A . Ensure that the project meets the committed time lines as this is the core objective and purpose of the project.
- B . Raise a change request to the change control board (CCB) to ask for funds to onboard new resources to expedite the project.
- C . Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking the proper response action.
- D . Ask the sponsor to start a new project to support the existing project and help it meet the original time line.
Suggested Answer: C