What should the project manager do next?

1 Posts
1 Users
0 Likes
186 Views
(@pesterfieldrayford)
Noble Member
Joined: 2 years ago
Posts: 681
Topic starter  

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

  • A . Review organizational process assets (OPAs) for clarity.
  • B . Document lessons learned before closing.
  • C . Consult the project charter for next steps.
  • D . Confirm the definition of done (DoD) has been met.

Show Answer Hide Answer

Suggested Answer: B

   