A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week.
What should the project manager do next?
- A . Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.
- B . Perform market research to find out if there are other vendors that can produce similar kinds of materials.
- C . Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.
- D . Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.
Suggested Answer: A