A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?
- A . Add temporary members with the specialized skill set to the team to accomplish the work with a high level of confidence.
- B . Assess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.
- C . Accept the work and outsource it to another team that has the specialized skill set; then integrate the solution,
- D . Reject the work from this team's backlog and ask the product owner to add It to another team's backlog.
Suggested Answer: B