Topic starter
14/07/2022 5:39 pm
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
- A . Revise the project schedule
- B . Present the project to the stakeholder
- C . Inform the client about the change
- D . Update the risk register with a new risk
Suggested Answer: B