A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical complexity of the project .
What should the project manager do before communicating with the client during the regular project progress meeting?
- A . Tell the client about the chance for the potential delay.
- B . Work with the project team to evaluate the potential delay.
- C . Do not disclose the likelihood of a delay as it is yet to happen.
- D . Ask the project sponsor to inform the client in the next update.
Suggested Answer: B