Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable .
What should the project manager do?
- A . Evaluate the impact of skipping the quality check for the deliverable.
- B . Seek approval from the sponsor on an extension of the project schedule,
- C . Seek approval from the quality board to skip the quality check.
- D . Ask the team member to work overtime to complete the quality check.
Suggested Answer: A