A project manager Is leading an agile software development project with strict deadlines. The client complained that the last deployment did not meet the acceptance criteria. The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications
What should the project manager do?
- A . Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible
- B . Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue
- C . Meet with the client and discuss the project deadlines
- D . Seek approval for more time for rework and resolve the issue
Suggested Answer: B