A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.
What should the project manager do?
- A . Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline
- B . Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change
- C . Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline
- D . Absorb the additional cost for the additional resources internally so that the project completes within the timeline
Suggested Answer: C