What should the pro...
 
Notifications
Clear all

What should the project manager do?

1 Posts
1 Users
0 Likes
143 Views
(@colmenerocarmelo)
Noble Member
Joined: 2 years ago
Posts: 746
Topic starter  

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

  • A . Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.
  • B . Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.
  • C . Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,
  • D . Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Show Answer Hide Answer

Suggested Answer: A

   
Quote

Latest PMI PMP Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: