A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?
- A . Reject the risk because the team is not in agreement on escalating it
- B . Include the risk in the risk assessment and evaluate it with the team
- C . Accept the risk and immediately enter the risk into the risk register
- D . Discuss with the consultant to understand why the risk was escalated
Suggested Answer: A