A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

  • A . Report the issue during the next status meeting at the end of the week
  • B . Escalate the issue to the project sponsor and upper management
  • C . Close out the project and tell the manager to open a service desk ticket
  • D . Log the issue and assign it to the project team member(s).

Show Answer Hide Answer

Suggested Answer: C

   