A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
- A . Escalate the issues to the project sponsor.
- B . Review the issues log to ensure the issues are captured.
- C . Check the risk management plan to ensure there is a strategy to address the issues.
- D . Ask the key stakeholders to discuss the issues with the project team.
Suggested Answer: B