What should the newly assigned project manager do first to understand the issues?

1 Posts
1 Users
0 Likes
157 Views
 Chi
(@jamiesonchi)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

  • A . Escalate the issues to the project sponsor.
  • B . Review the issues log to ensure the issues are captured.
  • C . Check the risk management plan to ensure there is a strategy to address the issues.
  • D . Ask the key stakeholders to discuss the issues with the project team.

Show Answer Hide Answer

Suggested Answer: B

   